Whittier Bridge/I-95 Improvement Project
What's New

On Wednesday, February 27, 2013, the Massachusetts Department of Transportation (MassDOT) Board of Directors approved a construction contract for the Whittier Bridge/I-95 Improvement Project. For more information, please see the Media Advisory

Whittier Bridge Statistics
58 years old
1,346 feet long
73,000 vehicles/day (current)
81,000 vehicles/day (2012 projected)



Preliminary Project Schedule

Start Development of Environmental Level Options: November 2008
Start Public Outreach: March 2009
File Environmental Notification Form (ENF): June 1, 2009
Submit Draft EIR/EA: Summer 2011
Public Review of Draft EIR/EA: Fall 2011
File Final EIR: Spring 2012
MEPA/NEPA Approvals: Spring 2012
Design Public Hearing: Spring 2012
Advertise Design/Build Contract: Spring 2012
Construction Start: Spring 2013