Start Development of Environmental Level Options: November 2008
|
|
•
|
Start Public Outreach: March 2009
|
|
•
|
File Environmental Notification Form (ENF): June 1, 2009
|
|
•
|
Submit Draft EIR/EA: Summer 2011
|
|
•
|
Public Review of Draft EIR/EA: Fall 2011
|
|
•
|
File Final EIR: Spring 2012
|
|
•
|
MEPA/NEPA Approvals: Spring 2012
|
|
•
|
Design Public Hearing: Spring 2012
|
|
•
|
Advertise Design/Build Contract: Spring 2012
|
|
•
|
Construction Start: Spring 2013
|
|
|
|
|